Delridge Pedestrian Bridge Seismic Project Updates

Stay up to date about the Delridge Pedestrian Bridge



Seattle Department of Transportation logo



Delridge Pedestrian Bridge Seismic Project Updates

Construction updates: October 3, 2024

Construction to help the Delridge Pedestrian Bridge better withstand earthquakes is ongoing! Last week, crews poured concrete to reinforce the west half of the bridge’s superstructure. They are working on pouring concrete to reinforce two of the bridge’s piers this week as well as finishing retrofits to the fascia walls on the west side and handrails. In the coming weeks, crews will begin working on the east half of the superstructure. 

We are closing sidewalks and car lanes under the bridge on Delridge Way SW in three phases to divert people walking, rolling, biking, and driving where work is occurring. On *Monday, October 7, 2024, we will be transitioning into our second phase of sidewalk and lane closures*. During this phase, Delridge Way SW will be reduced to one lane in each direction, with car traffic shifted to the west. Between SW Genesee St and SW Oregon St, the sidewalk on the east side of Delridge Way SW will also be closed while crews work on the east side of the bridge. In addition, *no street parking will be allowed on the east side of Delridge Way SW while this phase is in effect*. 

The map below shows the upcoming sidewalk and lane closures: 

Delridge BSR Detour Map [20241003]

At least one lane of travel in each direction and a sidewalk on one side of the street will be maintained throughout each phase. Please visit our project webpage [ https://www.seattle.gov/transportation/projects-and-programs/programs/bridges-stairs-and-other-structures/bridges/delride-pedestrian-bridge?utm_medium=email&utm_source=govdelivery ] to learn more about how travel will be impacted during each phase. 

The *Delridge Pedestrian Bridge is closed to all people walking, biking, and rolling for the duration of construction* (up to 12 months) to ensure their safety and allow our crews to work as efficiently as possible. As a reminder, we anticipate that construction will last approximately 12 months. Construction schedules are subject to change and depend on factors such as weather and availability of crews and materials. 

We will continue to provide updates on construction activities on our project webpage [ https://www.seattle.gov/transportation/projects-and-programs/programs/bridges-stairs-and-other-structures/bridges/delride-pedestrian-bridge?utm_medium=email&utm_source=govdelivery ] and via these email updates. Please feel free to share this email with your neighbors and encourage them to sign up for our email updates [ https://public.govdelivery.com/accounts/WASEATTLE/subscriber/new?qsp=WASEATTLE_8 ] to stay informed on the project.    

*What to expect during construction*    

We understand our closure of the Delridge Pedestrian Bridge for the duration of construction and phases of sidewalk and lane closures impacts everyone who uses the bridge and Delridge Way SW regularly. We are actively working to ensure our traffic control plan runs smoothly and impacts travelers as little as possible. 

In addition to the phases of sidewalk and lane closures, you can expect:       


* A full closure of the bridge during construction 

* Work in the public right-of-way near your home or business  

* Temporary on-street parking restrictions, with "no park" signs placed 72 hours in advance 

* Staged construction equipment and materials as well as noise, dust, and vibrations in the work area 

* Typical weekday work hours of 7 AM – 5 PM, Monday through Friday 

________________________________________________________________________



*Thank you! *     

Thank you for your interest in the Delridge Pedestrian Bridge Seismic project and for your patience during construction.    

Sincerely,       

Matthew Howard 

Communications and Outreach Lead      

Delridge Pedestrian Bridge Seismic Project   

"You are receiving this email because you have expressed interest in receiving updates on the Delridge Pedestrian Bridge Seismic project." 






*Seattle Department of Transportation*

700 5th Avenue

Suite 3800

Seattle, WA 98104

*Phone: 206-684-7623*

facebook [ https://www.facebook.com/SeattleDOT/?utm_medium=email&utm_source=govdelivery ]front porch [ https://sdotblog.seattle.gov/?utm_medium=email&utm_source=govdelivery ]r s s feed [ https://sdotblog.seattle.gov/feed/?utm_medium=email&utm_source=govdelivery ]twitter [ https://twitter.com/seattledot?utm_medium=email&utm_source=govdelivery ]flickr [ https://www.flickr.com/photos/sdot_photos?utm_medium=email&utm_source=govdelivery ]instagram [ https://www.instagram.com/seattledot/?utm_medium=email&utm_source=govdelivery ]youtube [ https://www.youtube.com/seattledot?utm_medium=email&utm_source=govdelivery ]linkedin [ https://www.linkedin.com/company/seattle-department-of-transportation?utm_medium=email&utm_source=govdelivery ] seattle dot gov

Manage Preferences [ https://public.govdelivery.com/accounts/WASEATTLE/subscriber/edit?preferences=true#tab1 ]  |  Unsubscribe [ https://public.govdelivery.com/accounts/WASEATTLE/subscriber/one_click_unsubscribe?verification=5.7e4abd93610d77ba0dce3e5196581a5c&destination=mshinji3056%40gmail.com ]  |  Contact Us [ https://www.seattle.gov/transportation/about-sdot/contact-us?utm_medium=email&utm_source=govdelivery ]  |  Help [ https://subscriberhelp.govdelivery.com/ ] |  Privacy [ https://www.seattle.gov/privacy-statement?utm_medium=email&utm_source=govdelivery ]




________________________________________________________________________

This email was sent to mshinji3056@gmail.com using GovDelivery Communications Cloud on behalf of: City of Seattle, Washington · 707 17th St, Suite 4000 · Denver, CO 80202 GovDelivery logo [ https://subscriberhelp.granicus.com/?utm_medium=email&utm_source=govdelivery ]

body .abe-column-block { min-height: 5px; } table.gd_combo_table img {margin-left:10px; margin-right:10px;} table.gd_combo_table div.govd_image_display img, table.gd_combo_table td.gd_combo_image_cell img {margin-left:0px; margin-right:0px;} table.govd_hr {min-width: 100%;}
  • [登録者]City of Seattle
  • [言語]日本語
  • [エリア]Seattle, WA
  • 登録日 : 2024/10/03
  • 掲載日 : 2024/10/03
  • 変更日 : 2024/10/03
  • 総閲覧数 : 0 人
Web Access No.2212287