Ballard Bridge Will Remain Open This Weekend + 15th Ave W/NW & Ballard Bridge Construction Update

October 3, 2024 Construction update



Seattle Department of Transportation logo



Ballard Bridge Will Remain Open This Weekend + 15th Ave W/NW & Ballard Bridge Construction Update – October 3, 2024

*The Ballard Bridge closure scheduled for October 4 through October 7 is cancelled. The bridge will remain open this weekend. The next scheduled full bridge closure is from 10 PM on Friday, October 11 to approximately 5 AM on Monday, October 14. * 

*Please note:* Bridge closure dates and times may change based on weather conditions, crew and materials availability, or other circumstances. You can get the latest information on our project webpage [ http://project%20webpage/ ], through this weekly email update, or by following SDOT on Facebook [ https://www.facebook.com/SeattleDOT/?utm_medium=email&utm_source=govdelivery ] or X [ https://x.com/seattledot?utm_medium=email&utm_source=govdelivery ] (formerly Twitter). 

More information about the Ballard Bridge closure and how to get around is in SDOT’s blog post [ https://sdotblog.seattle.gov/2024/08/27/ballard-bridge-weekend-closures/?utm_medium=email&utm_source=govdelivery ]. 

In the coming weeks, we will continue work along the east side of 15th Ave NW at NW 54th St, NW 53rd St, and NW 52nd St. Work is also happening at NW Market St and W Emerson St. 

As always, Ballard businesses are open during construction. Please support them by shopping locally! 

________________________________________________________________________


Ballard Bridge Construction Map 10.03
Construction on 15th Ave NW

Crews continue to work along the east side of *15th Ave NW at NW Market St, NW 54**th** St, NW 53rd St, and NW 52nd St.* Through this construction we will upgrade ADA accessible ramps, rebuild sidewalk corners, install upgraded traffic signals and cameras, improve storm drainage, and repair the sidewalk and roadway in select areas. 

Crews will also plan to continue *overnight work at W Emerson St* to grind and overlay the asphalt roadway. This work is scheduled for October 7-8 and October 14-15.   

*What to Expect * 


* Construction is typically scheduled Mondays – Fridays from 7 AM – 5 PM. The bulk of the overnight work will be from 7 PM – 5 AM.  

* Overnight work is noisy but within allowable noise levels. You may hear loud humming and a sound like a big vacuum. You may also feel mild vibrations. 

* Paving dates may change based on weather conditions, crew and materials availability, or other circumstances. You may also smell odors associated with asphalt paving. 

* We will close driving lanes on 15th Ave NW and NW Market St near work areas. There will always be at least one lane open in each direction. The turn lanes will remain open at intersections.  

* We will close the sidewalk in work areas. There will be detour signs in place to direct you around construction.   

* We will close NW 54th St and NW 52nd St to thru traffic as needed between 17th Ave NW and 14th Ave NW. You will still be able to walk, roll, bike, or drive to businesses and homes on these streets.   

* We will temporarily move the D Line bus stops at 15th Ave NW and NW Market St. Please see bus stops for new locations and/or sign up for transit alerts [ https://kingcounty.gov/en/dept/metro/routes-and-service/schedules-and-maps/d-line.html?utm_medium=email&utm_source=govdelivery ].   

* We will temporarily change parking in some areas for construction staging and traffic control near work sites. 

________________________________________________________________________



Construction on Ballard Bridge

As a reminder, the Ballard bridge will be closed over several weekends in October to complete maintenance and preservation work on the 107-year-old bridge. *The next scheduled bridge closure is Friday, October 11 through Monday, October 14.* The last closure is scheduled for Friday evening, October 18, 2024, through Monday morning, October 21, 2024 

Lane closures may begin as early as 7 PM on Friday, with the bridge fully closed at 10 PM. The bridge is expected to reopen by approximately 5 AM the following Monday. For more information about the closures and how to get around, please read SDOT’s blog post [ https://sdotblog.seattle.gov/2024/08/27/ballard-bridge-weekend-closures/?utm_medium=email&utm_source=govdelivery ]. 

*Please note:* Bridge closure dates and times may change based on weather conditions, crew and materials availability, or other circumstances.  

If crews are unable to complete maintenance and preservation work during the scheduled bridge closures due to weather, weekday overnight partial bridge closures may occur so crews can complete the work. We recognize that closing Ballard Bridge can affect your travel plans, and we appreciate your patience and understanding. 

Ballard Bridge October Calendar

"Upcoming weekend closure dates for the Ballard Bridge in October 2024. Graphic: SDOT "

________________________________________________________________________



Recent construction in action!
Ballard Bridge Work 10/3 Pic 1

"Crews pour new roadway pavement on the Ballard Bridge. Photo: SDOT"

________________________________________________________________________



Contact Us & Share Project Updates 

Thank you for signing up for updates about the 15th Ave W/NW and Ballard Bridge Paving and Safety Project [ https://lnks.gd/l/eyJhbGciOiJIUzI1NiJ9.eyJidWxsZXRpbl9saW5rX2lkIjoxMDUsInVyaSI6ImJwMjpjbGljayIsInVybCI6Imh0dHBzOi8vd3d3LnNlYXR0bGUuZ292L3RyYW5zcG9ydGF0aW9uL3Byb2plY3RzLWFuZC1wcm9ncmFtcy9wcm9ncmFtcy9tYWludGVuYW5jZS1hbmQtcGF2aW5nL2N1cnJlbnQtcGF2aW5nLXByb2plY3RzLzE1dGgtYXZlLXcvbnctYW5kLWJhbGxhcmQtYnJpZGdlLXBhdmluZy1wcm9qZWN0P3V0bV9tZWRpdW09ZW1haWwmdXRtX3NvdXJjZT1nb3ZkZWxpdmVyeSIsImJ1bGxldGluX2lkIjoiMjAyNDA3MDUuOTcyMTEwMzEifQ.zZLzEJN80MB-7LCoZEn44luezpoCB3ucl6xebh-HSkU/s/3165775075/br/245289064409-l?utm_medium=email&utm_source=govdelivery ]. We encourage you to share this message with your neighbors. They can also stay informed by signing up for email updates [ https://lnks.gd/l/eyJhbGciOiJIUzI1NiJ9.eyJidWxsZXRpbl9saW5rX2lkIjoxMDYsInVyaSI6ImJwMjpjbGljayIsInVybCI6Imh0dHBzOi8vcHVibGljLmdvdmRlbGl2ZXJ5LmNvbS9hY2NvdW50cy9XQVNFQVRUTEUvc3Vic2NyaWJlci9uZXciLCJidWxsZXRpbl9pZCI6IjIwMjQwNzA1Ljk3MjExMDMxIn0.YsEni1qDnCc8TI6cWe-qr6kWEnCTOMdoxIDYiRO5-Ss/s/3165775075/br/245289064409-l?utm_medium=email&utm_source=govdelivery ]. 

You can learn more on our project webpage [ https://lnks.gd/l/eyJhbGciOiJIUzI1NiJ9.eyJidWxsZXRpbl9saW5rX2lkIjoxMDcsInVyaSI6ImJwMjpjbGljayIsInVybCI6Imh0dHBzOi8vd3d3LnNlYXR0bGUuZ292L3RyYW5zcG9ydGF0aW9uL3Byb2plY3RzLWFuZC1wcm9ncmFtcy9wcm9ncmFtcy9tYWludGVuYW5jZS1hbmQtcGF2aW5nL2N1cnJlbnQtcGF2aW5nLXByb2plY3RzLzE1dGgtYXZlLXcvbnctYW5kLWJhbGxhcmQtYnJpZGdlLXBhdmluZy1wcm9qZWN0P3V0bV9tZWRpdW09ZW1haWwmdXRtX3NvdXJjZT1nb3ZkZWxpdmVyeSIsImJ1bGxldGluX2lkIjoiMjAyNDA3MDUuOTcyMTEwMzEifQ.AuePcchNkx_x9vFIX9CHDO_x5vABzq7d_SXepL7SDpY/s/3165775075/br/245289064409-l?utm_medium=email&utm_source=govdelivery ] or contact us by:  


* Email: 15thAveW_NWpaving@Seattle.gov     

* Phone: (206) 512-3950 (leave a voicemail and we will return your call)   

Learn More about the Project [ https://www.seattle.gov/transportation/projects-and-programs/programs/maintenance-and-paving/current-paving-projects/15th-ave-w/nw-and-ballard-bridge-paving-project?utm_medium=email&utm_source=govdelivery ]
White bar to separate images on the pageWhite bar to separate images on the page
________________________________________________________________________



Funding

The 15th Ave W/NW and Ballard Bridge Paving and Safety Project is funded by the Levy to Move Seattle [ https://www.seattle.gov/transportation/about-us/funding/levy-to-move-seattle?utm_medium=email&utm_source=govdelivery ].   

________________________________________________________________________



Need a Translation?

The City of Seattle is paving 15th Ave W/NW from W Emerson St to NW 57th St. To request translation of these materials, call (206) 512-3950 [ tel:%20+1%20(206)%20651-3950 ]. 

Como parte del Programa de Pavimentación, financiado por el impuesto "Levy to Move Seattle", el Departamento de Transporte de Seattle (SDOT) estará pavimentando este verano 15th Ave W/NW entre W Emerson St y NW 57th St. Para solicitar la traducción de este material, llame al (206) 512-3950. 

作為「移動西雅圖交通徵稅鋪路計畫」的一部分,西雅圖交通部 (SDOT) 最早將於 2023 年夏季鋪設 15th Ave W/NW 從 W Emerson St 到 NW 57th St 的路面。如 需这些资料的译文,或是在会议时需要口译服务,请致电 (206) 512-3950 [ tel:%20+1%20(206)%20651-3950 ]。 






*Seattle Department of Transportation*

700 5th Avenue

Suite 3800

Seattle, WA 98104

*Phone: 206-684-7623*

facebook [ https://www.facebook.com/SeattleDOT/?utm_medium=email&utm_source=govdelivery ]front porch [ https://sdotblog.seattle.gov/?utm_medium=email&utm_source=govdelivery ]r s s feed [ https://sdotblog.seattle.gov/feed/?utm_medium=email&utm_source=govdelivery ]twitter [ https://twitter.com/seattledot?utm_medium=email&utm_source=govdelivery ]flickr [ https://www.flickr.com/photos/sdot_photos?utm_medium=email&utm_source=govdelivery ]instagram [ https://www.instagram.com/seattledot/?utm_medium=email&utm_source=govdelivery ]youtube [ https://www.youtube.com/seattledot?utm_medium=email&utm_source=govdelivery ]linkedin [ https://www.linkedin.com/company/seattle-department-of-transportation?utm_medium=email&utm_source=govdelivery ] seattle dot gov

Manage Preferences [ https://public.govdelivery.com/accounts/WASEATTLE/subscriber/edit?preferences=true#tab1 ]  |  Unsubscribe [ https://public.govdelivery.com/accounts/WASEATTLE/subscriber/one_click_unsubscribe?verification=5.7e4abd93610d77ba0dce3e5196581a5c&destination=mshinji3056%40gmail.com ]  |  Contact Us [ https://www.seattle.gov/transportation/about-sdot/contact-us?utm_medium=email&utm_source=govdelivery ]  |  Help [ https://subscriberhelp.govdelivery.com/ ] |  Privacy [ https://www.seattle.gov/privacy-statement?utm_medium=email&utm_source=govdelivery ]




________________________________________________________________________

This email was sent to mshinji3056@gmail.com using GovDelivery Communications Cloud on behalf of: City of Seattle, Washington · 707 17th St, Suite 4000 · Denver, CO 80202 GovDelivery logo [ https://subscriberhelp.granicus.com/?utm_medium=email&utm_source=govdelivery ]

body .abe-column-block { min-height: 5px; } table.gd_combo_table img {margin-left:10px; margin-right:10px;} table.gd_combo_table div.govd_image_display img, table.gd_combo_table td.gd_combo_image_cell img {margin-left:0px; margin-right:0px;} table.govd_hr {min-width: 100%;}
  • [등록자]City of Seattle
  • [언어]日本語
  • [지역]Seattle, WA
  • 등록일 : 2024/10/03
  • 게재일 : 2024/10/03
  • 변경일 : 2024/10/03
  • 총열람수 : 47 명
Web Access No.2212759