ルート検索

住所を入力して検索ボタンをクリックすると、ルートが表示されます。

メールアドレス :   

登録内容

  • [登録者] : City of Seattle
  • [言語]日本語
  • [エリア]Seattle, WA
  • 登録日 : 2024/10/25
  • 掲載日 : 2024/10/25
  • 変更日 :2024/10/25
  • 総閲覧数 : 41 人
お知らせ

Beacon Ave S & 15th Ave S Safety Project Update - October 25

Construction updates for October 28 - November 8



Seattle Department of Transportation logo



Beacon Ave S & 15th Ave S Safety Project Update

________________________________________________________________________



*Construction of the Beacon Ave S and 15th Ave S Safety Project began on July 22!* Crews will work in segments along the project area through spring 2025.

Continue visiting our project website [ https://www.seattle.gov/transportation/projects-and-programs/programs/bike-program/protected-bike-lanes/beacon-hill-bike-route?utm_medium=email&utm_source=govdelivery ] or subscribe to our email list [ https://public.govdelivery.com/accounts/WASEATTLE/subscriber/topics?qsp=WASEATTLE_8 ] for bi-weekly updates on construction activities. 

________________________________________________________________________



Construction update

Over the next few weeks, you’ll see the following construction activities in the project area: 

*Weekend work: Beacon Ave S and S Lander St* 


* Crews will work with King County Metro to shift trolley wires *as early as the weekend of October 26 and 27. * 

*
* *Beacon Ave S will be temporarily reduced to one direction during this work.* Detours will direct people driving to use 17th Ave S between S College St and S McClellan St while crews work on the northbound or southbound side of the road. 
* The bus stops just south of the intersection of S Lander St on 15th Ave S will be temporary relocated to the west side of Red Apple along 15th Ave S
* The bus stops just north of the intersection of S Hanford St on 15th Ave S will be temporary relocated to the west side of Red Apple along 15th Ave S. 


* Tree removals in this area are postponed until early 2025. 

*15th Ave S from S Judkins St to S State St* 


* Crews will continue installing concrete buffer for protected bike lanes on the *east and west sides* of 15th Ave S from S Judkins St to S State St. This work will *permanently remove parking *on the east side of 15th Ave S from S Judkins St to S State St. 

* Crews will pour concrete for new sections of roadway, driveway, sidewalk, and curb ramps on the *east and west sides *of 15th Ave S 

*15th Ave S near S Massachusetts St and S State St* 


* Crews will do restoration work and place top soil on the *east and west sides* of 15th Ave S 

* Crews will pour concrete for sidewalk and driveway on the *west side* of 15th Ave S 

*15th Ave S near S Grand St and S Holgate St* 


* Crews will pour concrete for sidewalks and do restoration work on the *east and west sides* of 15th Ave S 

*15th Ave S and S Plum St* 


* Crews excavate, install storm drain improvements, and pour new roadway, sidewalk, and curb ramps on the *west side* of 15th Ave S 

* Crews install concrete buffer for protected bike lanes on the *east and west sides* of 15th Ave S from S Plum St to S College St.  

*15th Ave S and S College St* 


* Crews will continue installing storm drain and electrical improvements, and then pour new roadway, sidewalk, and curb ramps on the *east side* of 15th Ave S 

* Crews will remove roadway pavement and sidewalk and begin installing storm drain and electrical improvements on the* west* *side* of 15th Ave S 

*Traffic Control* 


* 15th Ave S will be reduced to one lane 24/7 during this work. Drivers and cyclists will use 14th Ave S between 15th Ave S and S College St as a detour. 

* Pedestrian detours will direct people walking to cross to the opposite side of 15th Ave S while crews work on the east or west side of the road*.* 

* Parking restrictions will remain in place 

* Please visit the King County Metro website [ https://kingcounty.gov/en/dept/metro/rider-tools/service-advisories?utm_medium=email&utm_source=govdelivery ] for rider alerts 

* A uniformed police officer will direct northbound and southbound travelers through intersections during work requiring lane blockages or signal modifications 

* S College St between 15th Ave S and 16th Ave S will be closed. Local access to S College St will be maintained.  

________________________________________________________________________



*Tree Removals*

We may need to remove more trees than the three we initially identified during design phase. As we began sidewalk repair work on the project corridor, we're finding that more trees have root systems that are too shallow and overgrown under the sidewalk. We have exhausted all design options to build ADA-compliant sidewalks and will need to remove additional trees - these trees have been posted. We are trying our best to retain as many trees as possible. We will continue to inspect tree roots as we move southward with our sidewalk repair work and will share additional information about tree removals as they become available.

________________________________________________________________________



*Construction progress*
Crews removing existing sidewalk on 15th Ave S near S Judkins St

Crews removing existing sidewalk on 15th Ave S near S Judkins St

Crews smooth out newly paved sidewalk on 15th Ave S near S Judkins St

Crews smooth out newly paved sidewalk on 15th Ave S near S Judkins St

________________________________________________________________________



*Business owners and managers*

Please fill out this construction survey [ https://survey.alchemer.com/s3/7863357/6592169a0975?utm_medium=email&utm_source=govdelivery ] so we can keep you informed and minimize impacts to your business during construction. You may also request a paper copy by leaving us a voicemail at (206) 900-8728 [ tel:%20+1%20(206)%20900-8728 ] or emailing us at Beacon15thSafety@seattle.gov.

The survey is available in English, [ https://survey.alchemer.com/s3/7863357/6592169a0975?utm_medium=email&utm_source=govdelivery ]Spanish,  [ https://survey.alchemer.com/s3/7863357/3ff0336f0841?utm_medium=email&utm_source=govdelivery ]Amharic, [ https://survey.alchemer.com/s3/7863357/ac1329f48bc3?utm_medium=email&utm_source=govdelivery ]Simplified Chinese,  [ https://survey.alchemer.com/s3/7863357/11bd0e37baf6?utm_medium=email&utm_source=govdelivery ]Traditional Chinese,  [ https://survey.alchemer.com/s3/7863357/cfbd6fe8e97f?utm_medium=email&utm_source=govdelivery ]Tagalog,  [ https://survey.alchemer.com/s3/7863357/5571bc5da205?utm_medium=email&utm_source=govdelivery ]Vietnamese,  [ https://survey.alchemer.com/s3/7863357/e4e2685140d2?utm_medium=email&utm_source=govdelivery ]Somali, [ https://survey.alchemer.com/s3/7863357/eb9a76299b2c?utm_medium=email&utm_source=govdelivery ]and Tigrinya. [ https://survey.alchemer.com/s3/7863357/1dfc6c9a0261?utm_medium=email&utm_source=govdelivery ]

Thank you to all the business owners and managers who have already filled out our survey online or in-person during our door-to-door outreach in late June and early July!

________________________________________________________________________



*What to Expect During Construction*

Typical work hours are Monday – Friday, from 7:00 AM to 5:00 PM. During this time you can expect: 


* Temporary traffic revisions to accommodate construction vehicles
* Temporary parking restrictions near work zone
* Noisy construction activities, such as backup alarms for safety, heavy vehicle use, and the use of power tools.
* Please note that much of this work is weather dependent and subject to schedule changes. 

________________________________________________________________________



Changes coming to Beacon Ave S and 15th Ave S

* *Repaired sections of sidewalk* near every intersection along the entire route
* *New APS pedestrian push buttons* at every crossing at S Hanford St and Beacon Ave S and at the south and west crossings of 15th Ave S and S College St
* *62 new or rebuilt curb ramps*. When this project is complete, people who use wheels will be able to safely travel from Dr. Jose Rizal Bridge to S Spokane St.
* *Concrete-protected bike lanes* on both sides of 15th Ave S
* *Post-protected bike lanes* on both sides of Beacon Ave S
* *New bike signals* at the intersections of S Charles St & Golf Dr S, 15th Ave S & S College St, and 15th Ave S & Beacon Ave S
* *New bus stop islands* on both sides of Beacon Ave S at S Hanford St and outside of Beacon Hill Station
Map illustrating changes coming to Beacon Ave S and 15th Ave S

Changes coming to Beacon Ave S and 15th Ave S as part of this Safety Project

Learn more about how we're improving safety in North Beacon Hill [ https://www.seattle.gov/transportation/projects-and-programs/programs/bike-program/protected-bike-lanes/beacon-hill-bike-route?utm_medium=email&utm_source=govdelivery ]

________________________________________________________________________



How to stay informed

* Call our project hotline at (206) 900-8728 [ tel:%20+1%20(206)%20900-8728 ]
* Email us at Beacon15thSafety@seattle.gov.
* Visit our project webpage [ https://www.seattle.gov/transportation/projects-and-programs/programs/bike-program/protected-bike-lanes/beacon-hill-bike-route?utm_medium=email&utm_source=govdelivery ] to:
* Read about project progress
* Sign up for email updates

Thank you,

Ching Chan

Public Engagement Lead

Levy to Move Seattle Logo
________________________________________________________________________



For translation services, please call (206) 900-8728 [ tel:%20+1%20(206)%20900-8728 ] and leave a message clearly stating the language you prefer.

________________________________________________________________________



Blue Bullhorn Icon
 
Sign up for the SDOT Newsletter

"Stay up to date on Seattle's transportation news. You'll receive our top highlights delivered straight to your inbox each month. – ""Subscribe here" [ https://links-1.govdelivery.com/CL0/https:%2F%2Fpublic.govdelivery.com%2Faccounts%2FWASEATTLE%2Fsubscriber%2Fnew%3Ftopic_id=WASEATTLE_353/1/0100019230e79298-055f5089-b93c-47aa-a827-b292f38c3bfa-000000/QdPe2xxfScc_oOXY7XV7dmtfjxyoDDb0uUhDZMvDh8I=372 ]". " [ https://sdotblog.seattle.gov/2024/09/24/mayor-harrells-2025-2026-proposed-budget-for-sdot/?utm_medium=email&utm_source=govdelivery ]








*Seattle Department of Transportation*

700 5th Avenue

Suite 3800

Seattle, WA 98104

*Phone: 206-684-7623*

facebook [ https://www.facebook.com/SeattleDOT/?utm_medium=email&utm_source=govdelivery ]front porch [ https://sdotblog.seattle.gov/?utm_medium=email&utm_source=govdelivery ]r s s feed [ https://sdotblog.seattle.gov/feed/?utm_medium=email&utm_source=govdelivery ]twitter [ https://twitter.com/seattledot?utm_medium=email&utm_source=govdelivery ]flickr [ https://www.flickr.com/photos/sdot_photos?utm_medium=email&utm_source=govdelivery ]instagram [ https://www.instagram.com/seattledot/?utm_medium=email&utm_source=govdelivery ]youtube [ https://www.youtube.com/seattledot?utm_medium=email&utm_source=govdelivery ]linkedin [ https://www.linkedin.com/company/seattle-department-of-transportation?utm_medium=email&utm_source=govdelivery ] seattle dot gov

Manage Preferences [ https://public.govdelivery.com/accounts/WASEATTLE/subscriber/edit?preferences=true#tab1 ]  |  Unsubscribe [ https://public.govdelivery.com/accounts/WASEATTLE/subscriber/one_click_unsubscribe?verification=5.7e4abd93610d77ba0dce3e5196581a5c&destination=mshinji3056%40gmail.com ]  |  Contact Us [ https://www.seattle.gov/transportation/about-sdot/contact-us?utm_medium=email&utm_source=govdelivery ]  |  Help [ https://subscriberhelp.govdelivery.com/ ] |  Privacy [ https://www.seattle.gov/privacy-statement?utm_medium=email&utm_source=govdelivery ]




________________________________________________________________________

This email was sent to mshinji3056@gmail.com using GovDelivery Communications Cloud on behalf of: City of Seattle, Washington · 707 17th St, Suite 4000 · Denver, CO 80202 GovDelivery logo [ https://subscriberhelp.granicus.com/?utm_medium=email&utm_source=govdelivery ]

body .abe-column-block { min-height: 5px; } table.gd_combo_table img {margin-left:10px; margin-right:10px;} table.gd_combo_table div.govd_image_display img, table.gd_combo_table td.gd_combo_image_cell img {margin-left:0px; margin-right:0px;} table.govd_hr {min-width: 100%;}

びびなび - 自治体からのお知らせ

印刷された情報をサイトで見るには、上記URLまたはQRコードからアクセスできます。