Fremont Construction Starting May 12: Route 40 Transit-Plus Multimodal Corridor Project – May 9 Update

Fremont Construction Starting May 12: Route 40 TPMC



City of Seattle Logo



Route 40 TPMC logo
________________________________________________________________________



Construction in Fremont begins May 12

Fremont Project Area

Fremont project area: N 36th St between 2nd Ave NW and N 35th St, and Fremont Ave N between N 34th and N 36th St

Dear Community Members, 

*Construction in Fremont begins the week of May 12. *We will start on street and watermain upgrades on Fremont Ave N between N 34th St and N 35th St. As part of this work, there is also a scheduled* street closure on May 17 *on Fremont Ave N between N 34th and N 35th St.

To learn more about what’s happening in the Fremont neighborhood, please visit our webpage [ https://www.seattle.gov/transportation/projects-and-programs/programs/transit-program/transit-plus-multimodal-corridor-program/route-40---transit-plus?utm_medium=email&utm_source=govdelivery#materials ] and check out the construction area [ https://www.seattle.gov/documents/Departments/SDOT/TransitProgram/Route%2040%20TPMC/Route_40_Fremont_Construction_Plans_Webapge.pdf?utm_medium=email&utm_source=govdelivery ] and construction activities [ https://www.seattle.gov/documents/Departments/SDOT/TransitProgram/Route%2040%20TPMC/Construction_Scope_Definitions_Route%2040.pdf?utm_medium=email&utm_source=govdelivery ]. Construction in the Fremont neighborhood is scheduled through 2025.

*Water Main Infrastructure Upgrades*

We're working with Seattle Public Utilities (SPU) to replace a 100-year-old waterline under Fremont Ave N between N 34th St and N 35th St and inserting a new valve at Dayton Ave N and N 36th St. Completing the water main upgrades and the street upgrades at the same time will help reduce impacts to the community by coordinating major construction projects. This approach helps minimize travel disruptions, lower construction costs, and shorten the overall construction timeline compared to completing the projects separately.

When complete, the watermain upgrades are expected to:


* Improve capacity to deliver drinking water in your neighborhood
* Improve water system flow and pressure
* Ensure water service reliability and reduce disruptions by creating more backups in the system

*What to Expect:*

Water service impacts will vary based on construction progress and the location of infrastructure upgrades. Specific buildings in Fremont will experience disruptions at different times throughout the project and for varying durations as we complete these essential improvements.

*Advance Notifications*

We are committed to keeping you informed:


* Notifications will be shared via the project email list *at least one week in advance.* You can subscribe *here [ https://us-west-2.protection.sophos.com?d=govdelivery.com&h=0fd3e4c5e2be4591827bf154146cd519&i=NjVlMjQ4NzM0ODMzNjA1ZjY4NzdkMzc3&p=m&s=AVNPUEhUT0NFTkNSWVBUSVYvMXkb5y1rh_jmhCD6q3lAKUrO49ywWjW_y-N0Uq9DQw&t=dWw4Q05TeEhDaHRIYllVOWxSME1RejBJWW55M2hXMEVLellJUDB4QWdiaz0%3D&u=aHR0cHM6Ly9wdWJsaWMuZ292ZGVsaXZlcnkuY29tL2FjY291bnRzL1dBU0VBVFRMRS9zdWJzY3JpYmVyL25ldz9xc3A9V0FTRUFUVExFXzg%3D&utm_medium=email&utm_source=govdelivery ].*
* Flyers with detailed information will also be distributed to buildings that will be impacted *five **days before the scheduled shut off*.

First Scheduled Water Shut Off on Saturday, May 17:

*Date:* Saturday, May 17

*Time:* Approximately 6 AM - 12 PM

*What to Expect:*


* This water shut off will require a* full street closure on Fremont Ave N between N 34th St and N 35th St*. We advise residents and commuters to plan ahead and use alternate routes during this time to avoid disruptions. Signage and traffic rerouting will be in place to assist with navigation. See map below
* The Fremont Bridge will be open to vehicles, and people walking, biking, and rolling
* Sidewalks will remain open and access to businesses will be maintained
* Bikes will need to dismount on Fremont Ave, between N 35th St and N 34th St
* Please watch for temporary detour signs

The below map shows the buildings that will be impacted by the water shut off on May 17

Watermain shutoff area for may 17

Fremont buildings impacted by the May 17 water shut off between 6 AM -12 PM

________________________________________________________________________



May 17 Traffic Map
May 17 Traffic Map

Traffic map on May 17. Fremont Ave N between N 34th and N 35th St will be closed.

________________________________________________________________________



As much as possible, we are actively working to reduce the area and duration of water shutoffs, as well as carefully planning their timing to minimize the impact on businesses that rely on access to water. This includes scheduling full street closures if it helps minimize the time residents are without water.

The project team is also mindful of the May 17 Parade [ https://us-west-2.protection.sophos.com?d=17thofmay.org&h=0fd3e4c5e2be4591827bf154146cd519&i=NjVlMjQ4NzM0ODMzNjA1ZjY4NzdkMzc3&p=m&s=AVNPUEhUT0NFTkNSWVBUSVYvMXkb5y1rh_jmhCD6q3lAKUrO49ywWjW_y-N0Uq9DQw&t=aDhDb0YxeUhmSDZxVDZqQkZneVpHZTZoaEYzRTZ2S1IrRms0RVRoYXBIVT0%3D&u=aHR0cHM6Ly93d3cuMTd0aG9mbWF5Lm9yZy8yMDI1LWV2ZW50cy9wYXJhZGU%3D&utm_medium=email&utm_source=govdelivery ] in Ballard and have ensured that construction will not interfere with the event, set to take place later in the afternoon.

Our team is actively providing affected business owners and residents with the most up-to-date information. If you have any specific questions or require further assistance, please reach out to us at Route40@seattle.gov

You can learn how best to prepare for water main work by visiting  SPU's webpage [ https://www.seattle.gov/utilities/neighborhood-projects/water-outages/planning-for-outages?utm_medium=email&utm_source=govdelivery ] for tips on preparing for a water outage.   

________________________________________________________________________



Temporary bus stops during Fremont construction

As crews mobilize for work in Fremont, please note that buses will be rerouted around the active work zone to temporary stops for Routes 31, 32, 40, and 62. 

*Where will the temporary bus stops be?*

Temp bus stops
* The northbound Route 40 stop on Fremont Ave N will be rerouted to Fremont Pl N and N 36th St near the Lenin statue
* Routes 31, 32, and 62 buses that also use the northbound Fremont Ave N stop will have a temporary bus zone on N 35th St just east of Fremont Ave N.
* Southbound Routes 31, 32, and 62 buses will be rerouted from N 35th St to N 34th St via Stone Way N. There will be a temporary bus zone on the west side of Stone Way N between N 35th St and N 34th St
* The southbound stop on Fremont Ave N served by Routes 31, 32, 40, and 62 will be temporarily relocated to the far side of N 34th St, approximately 300-400 feet south of the current stop

Metro riders can expect these new temporary stops to serve these routes as early as May 12. These temporary bus stops are anticipated to serve riders through 2025.

________________________________________________________________________



What’s Happening on Westlake Ave N?

Please visit our project webpage for detailed construction updates and neighborhood impacts along Westlake Ave N. This includes:


* *8th Ave N and Galer St*: Full closure of 8th Ave N at Westlake Ave N between May 9-11. Originally, overnight work was anticipated but this has since been scheduled to be completed during the day. Construction and temporary lane reductions are expected throughout the month of May
* *Aloha St and 9th Ave N*: Trenching and sidewalk improvements throughout May. Please expect vehicle lane reductions and follow pedestrian and bicycle detour routes and signs.
* The bicycle detour near Westlake Ave N and 9th Ave N and Aloha St will last until the middle of the week of May 12, and we plan to reopen it for bicyclists after. Please follow all detours necessary and use caution when traveling on your bicycle. Thank you for your patience and understanding

________________________________________________________________________



Route 40 Ridership is on the Rise

 Over *8,800 average weekday daily boardings [ https://app.powerbigov.us/view?r=eyJrIjoiZDMwMWExOTMtOTY3ZC00MTU5LTgxMDgtODM4MTZiYTExMzJkIiwidCI6ImJhZTUwNTlhLTc2ZjAtNDlkNy05OTk2LTcyZGZlOTVkNjljNyJ9&utm_medium=email&utm_source=govdelivery ]* as of March 2025 – a 10% increase from March 2024

Project Benefits

In addition to the 5-10% transit travel time savings, 14-17% in Ballard to Downtown, the Route 40 project will maintain and modernize vital infrastructure

Route 40 infographic
________________________________________________________________________



What you can expect during construction

* Temporary lane reductions
* Temporary driveway closures
* Temporary bus stop closures
* Temporary parking restrictions
* Temporary sidewalk detours
* Temporary storage of construction supplies in the street  
* Temporary noise, dust and vibrations
* Bus stop relocations
* Drainage work: This involves digging trenches and installing pipe and inlet structures to help manage surface water runoff
* Signal pole foundation installation: Concrete foundations with bolts to attach the new signal poles and pedestrian pushbutton posts will be poured in conjunction with sidewalk work
* Trenching for conduit: This involves digging trenches to lay down pipes or cables underground
* Sidewalk curb bulb out: This involves making the curbs stick outward for safety or accessibility
* Full depth street replacement: Fremont Ave N between N 34th and N 35th St will be completely replaced with concrete paving
* Mill and fill overlay: This is when the top layer of the street gets removed and replaced with new asphalt

The construction timeline is always subject to change depending on weather conditions and materials availability. We are committed to keeping you informed and maintaining open communication throughout the remainder of this project. To learn more about the project and designs, visit our online open house.  [ https://route40.infocommunity.org/?utm_medium=email&utm_source=govdelivery ]

________________________________________________________________________



Local Business Spotlight

"If you own or manage a business in Fremont or Westlake Ave near the project corridor and would like to be featured, please email us at Route40@seattle.gov"" and send us a short description and picture of your business."

________________________________________________________________________



Contact Us & Share Project Updates 

Thank you for signing up for updates about the Route 40 Transit Plus Multimodal Corridor Project [ https://www.seattle.gov/transportation/projects-and-programs/programs/transit-program/transit-plus-multimodal-corridor-program/route-40---transit-plus?utm_medium=email&utm_source=govdelivery ]. We encourage you to share this message with your neighbors. They can also stay informed by signing up for email updates [ https://public.govdelivery.com/accounts/WASEATTLE/subscriber/new ].

You can learn more on our project webpage [ https://www.seattle.gov/transportation/projects-and-programs/programs/transit-program/transit-plus-multimodal-corridor-program/route-40---transit-plus?utm_medium=email&utm_source=govdelivery ] or contact us by: 


* Email: Route40@seattle.gov

* Phone: (206) 775-8731 [ tel:%20+1%20(206)%20775-8731 ] [ tel:%20+1%20(206)%20512-3950 ] (leave a voicemail and we will return your call)  

________________________________________________________________________



Other Projects Along This Route

Our project team is in close coordination with the following projects. Please visit their project webpage to see the latest update:


* 15th Ave NW and Ballard Bridge Paving and Safety Project [ https://www.seattle.gov/transportation/projects-and-programs/programs/maintenance-and-paving/current-paving-projects/15th-ave-w/nw-and-ballard-bridge-paving-project?utm_medium=email&utm_source=govdelivery ]
* Ship Canal Water Quality Project [ https://www.seattle.gov/utilities/neighborhood-projects/ship-canal?utm_medium=email&utm_source=govdelivery ]
* RapidRide J Line - Formerly RapidRide Roosevelt [ https://www.seattle.gov/transportation/projects-and-programs/programs/transit-program/transit-plus-multimodal-corridor-program/rapidride-roosevelt?utm_medium=email&utm_source=govdelivery ]
* N 102nd St/Aurora Ave N Pedestrian Bridge [ https://seattle.gov/transportation/projects-and-programs/programs/bridges-stairs-and-other-structures/bridges/n-102nd-st/aurora-ave-n-ped-bsr?utm_medium=email&utm_source=govdelivery ]
* 13th Ave NW/Holman Rd NW Pedestrian Bridge Seismic Retrofit [ https://seattle.gov/transportation/projects-and-programs/programs/bridges-stairs-and-other-structures/bridges/13th-ave-nw/holman-nw-bsr?utm_medium=email&utm_source=govdelivery ]
* "Missing Link" Bike Route Study on NW Market St - Leary Ave NW - 17th Ave NW [ https://www.seattle.gov/transportation/projects-and-programs/programs/bike-program/ballard-bike-route-study?utm_medium=email&utm_source=govdelivery ]
* Sound Transit Northgate Station [ https://www.soundtransit.org/system-expansion/northgate-station?utm_medium=email&utm_source=govdelivery ]

________________________________________________________________________



Translations

If you need this information translated, please call *206-775-8731 [ tel:206-775-8731 ]*.

如果您需要此信息翻譯成中文 請致電 *206-775-8731 [ tel:206-775-8731 ]*.

Kung kailangan mo ang impormasyon na ito na nakasalin sa Tagalog mangyari lamang na tumawag sa *206-775-8731 [ tel:206-775-8731 ]*.

Si necesita traducir esta información al español, llame al *206-775-8731 [ tel:206-775-8731 ]*.

Odeeffannoon kun akka siif *206-775-8731 [ tel:206-775-8731 ]*.

Nếu quý vị cần thông tin này chuyển ngữ sang tiếng Việt xin gọi *206-775-8731 [ tel:206-775-8731 ]*.

የዚህን መረጃ ትርጉም ከፈለጉ፣ በዚህ ስልክ ቁጥር ይደውሉ፡ *206-775-8731 [ tel:206-775-8731 ]*.

ናይዚ ሓበሬታ ትርጉም እንተደሊኹም፣ በዚ ቁጽሪ ስልኪ ይድውሉ፡ *206-775-8731 [ tel:206-775-8731 ]*.

당신이 번역이 정보를 필요로하는 경우에, *206-775-8731 [ tel:206-775-8731 ]* 로 전화 해주십시오.

اذا تريد ترجمة هذه المعلومات, يرجى الاتصال برقم
*206-775-8731 [ tel:206-775-8731 ]*






*Seattle City Hall*

600 4th Avenue

Seattle, WA 98104

*Phone: 206-684-2489 (CITY)*

facebook [ https://www.facebook.com/cityofseattlegov/?utm_medium=email&utm_source=govdelivery ]twitter [ https://twitter.com/cityofseattle?utm_medium=email&utm_source=govdelivery ]instagram [ https://www.instagram.com/cityofseattlegov/?utm_medium=email&utm_source=govdelivery ] [ https://twitter.com/cityofseattle?utm_medium=email&utm_source=govdelivery ] seattle dot gov

Manage Preferences [ https://public.govdelivery.com/accounts/WASEATTLE/subscriber/edit?preferences=true#tab1 ]  |  Unsubscribe [ https://public.govdelivery.com/accounts/WASEATTLE/subscriber/one_click_unsubscribe?verification=5.7e4abd93610d77ba0dce3e5196581a5c&destination=mshinji3056%40gmail.com ]  |  Contact Us [ http://www.seattle.gov/customerservice/contact.htm?utm_medium=email&utm_source=govdelivery ]  |  Help [ https://subscriberhelp.govdelivery.com/ ] |  Privacy [ https://www.seattle.gov/privacy-statement?utm_medium=email&utm_source=govdelivery ]




________________________________________________________________________

This email was sent to mshinji3056@gmail.com using GovDelivery Communications Cloud on behalf of: City of Seattle, Washington · 600 Fourth Avenue · Seattle, WA 98104 GovDelivery logo [ https://subscriberhelp.granicus.com/?utm_medium=email&utm_source=govdelivery ]

body .abe-column-block { min-height: 5px; } table.gd_combo_table img {margin-left:10px; margin-right:10px;} table.gd_combo_table div.govd_image_display img, table.gd_combo_table td.gd_combo_image_cell img {margin-left:0px; margin-right:0px;} table.govd_hr {min-width: 100%;}
  • [Registrant]City of Seattle
  • [Language]日本語
  • [Location]Seattle, WA
  • Posted : 2025/05/09
  • Published : 2025/05/09
  • Changed : 2025/05/09
  • Total View : 55 persons
Web Access No.2760287